74 – Barshinger Watershed Ren. – P1

Basic Information
Project Type: Stream Restoration
Project Status: Planned
Start Date: 2018
End Date: 2019
Cost: 1312500
Geography
Jurisdiction(s): York Twp
Latitude: 39.87106
Longitude: -76.66228
Project Area:
HUC 12 Watershed: 020503060602
Project Leng: 8750
Reductions (lbs/yr)
Nitrogen: 1750
Phosphorus: 595
Sediment: 474688
Description
Barshinger Watershed Ren. - P1 Stream Restoration
Additional Information
Joint / Multi-municipality Project:Yes
Secured Funding:Yes
Designs Prepared:Yes
Benefits:No
Within Impaired Watershed:Yes
Ownership Type:Private
NPDES Permit RequiredYes
Publicly AccessibleNo
Notes
Some items are unknown as the project is not being completed by York Township. Not a York township Project. York Township completed form so that there is something in file.
Land Use / Land Cover (LULC) Values
Individual land use / land cover classes Within project area (acres) Within treatment area (acres)