Basic Information
Project Type: Bioretention
Project Status: Planned
Start Date: 03-03-2018
End Date: 05-05-2018
Cost: 350000
Geography
Jurisdiction(s): York City
Latitude: 39.96351
Longitude: -76.71887
Project Area: 6.34
HUC 12 Watershed: 020503060705
Reductions (lbs/yr)
Nitrogen: 556
Phosphorus: 7
Sediment: 7733
Description
Altering the green islands in a previously completed streetscape project to capture and treat street runoff.
Additional Information
Joint / Multi-municipality Project:No
Secured Funding:No
Designs Prepared:No
Benefits:Yes
Within Impaired Watershed:Yes
Ownership Type:Public
NPDES Permit RequiredNo
Publicly AccessibleYes
Notes
This greenway represents a pathway between public schools, representing an educational opportunity.
Land Use / Land Cover (LULC) Values
Individual land use / land cover classes Within project area (acres) Within treatment area (acres)