Basic Information
Project Type: Pond retrofit
Project Status: Planned
Start Date: 04-03-2017
End Date: 08-31-2017
Cost: 10000
Geography
Jurisdiction(s): Hellam Twp
Latitude: 40.02514
Longitude: -76.62637
Project Area: 0.14
HUC 12 Watershed: 020503061703
Reductions (lbs/yr)
Nitrogen: 63
Phosphorus: 2
Sediment: 2288
Description
retrofit pond to control stormwater more appropriately
Additional Information
Joint / Multi-municipality Project:No
Secured Funding:No
Designs Prepared:No
Benefits:Yes
Within Impaired Watershed:Yes
Ownership Type:Private
NPDES Permit RequiredNo
Publicly AccessibleNo
Notes
The basin retrofit is on private property and will need the owners consent to retrofit. The Township would complete the project and the homeowner would be responsible for maintenance. This project would also assist in stormwater runoff issues downstream
Land Use / Land Cover (LULC) Values
Individual land use / land cover classes Within project area (acres) Within treatment area (acres)