Menu Account

York City Industrial Park -Basin

Basic Information
Project Type: pond retrofit
Project Status: Planned
Start Date: 03-09-2018
End Date: 07-27-2018
Cost: 100000
Geography
Jurisdiction(s): York City
Latitude: 39.98366
Longitude: -76.75114
Project Area: 4.56
HUC 12 Watershed: 020503060705
Reductions (lbs/yr)
Nitrogen: 161
Phosphorus: 4
Sediment: 5799
Description
retrofit of an existing rate control stormwater basin.
Additional Information
Joint / Multi-municipality Project:No
Secured Funding:No
Designs Prepared:No
Benefits:No
Within Impaired Watershed:Yes
Ownership Type:Private
NPDES Permit RequiredNo
Publicly AccessibleNo
Notes
Ownership issues and maintenance responsibility would need to be resolved with the dign work to provide a solid O&M plan post-construction work.
Land Use / Land Cover (LULC) Values
Individual land use / land cover classes Within project area (acres) Within treatment area (acres)